Moderate 3-6 weeks typical project $8,000-$35,000 CAD

Bathroom Renovation Budget Guide

Plan and budget for your bathroom renovation with realistic Ontario cost estimates and hiring tips.

Bathroom Renovation — Complete Planning Guide
Home RenoVision DIY · 2.5M+ views

What This Video Covers

  • Realistic bathroom renovation costs broken down by category
  • Materials comparison at different budget levels
  • Waterproofing essentials — what not to skip
  • Timeline expectations and how to plan around one-bathroom living

Safety Warnings

  • All plumbing and electrical work must be done by licensed tradespeople. Bathroom electrical must be GFCI protected.
  • Ensure proper ventilation. A bathroom fan (minimum 50 CFM) vented to the exterior is code-required in Ontario. Poor ventilation causes mould.
  • If your home is pre-1990, test for asbestos in floor tiles, plaster walls, and pipe insulation before demolition.

Step-by-Step Guide

1

Determine your renovation scope

A cosmetic refresh (paint, fixtures, accessories) costs $2,000-$5,000. A mid-range renovation (new vanity, tub, tile) runs $8,000-$18,000. A full gut renovation with layout changes costs $18,000-$35,000+.

2

Decide what stays and what goes

Keeping existing plumbing in place saves thousands. Moving a toilet, shower, or sink requires new plumbing rough-ins which dramatically increases cost. Work with your existing layout when possible.

3

Choose materials at different price points

Tiles: porcelain ($3-$8/sq ft) vs natural stone ($15-$30/sq ft). Vanities: prefab ($200-$800) vs custom ($1,500-$5,000). Fixtures: standard ($50-$200) vs premium ($300-$1,000+). Mix high and low strategically.

4

Hire a verified bathroom renovation contractor

Search ProScore for bathroom remodeling contractors with strong scores. For full renovations, look for HCRA-verified contractors. A dedicated bathroom contractor will cost more than a handyman but delivers significantly better results.

5

Understand hidden costs

Budget for: permits ($200-$500), plumbing rough-in changes ($1,500-$3,000), electrical updates ($500-$1,500), waterproofing ($500-$1,000), and unexpected issues behind walls (10% contingency).

6

Plan the timeline

A typical bathroom renovation takes 3-6 weeks. Demolition: 1-2 days. Plumbing/electrical rough-in: 2-3 days. Waterproofing: 1-2 days. Tile: 3-5 days. Fixtures and finishing: 2-3 days. Allow buffer for material delays.

7

Waterproofing is non-negotiable

Proper waterproofing in the shower and tub area prevents mould and structural damage. Ensure your contractor uses a membrane system (Schluter Kerdi or RedGard). This is not where you cut corners.

Rather hire a pro?

Find a trusted bathroom remodeling near you, verified across 15+ data sources with a ProScore rating you can trust.

Find a Verified Pro

Compare bathroom remodeling rated across 15+ verified data sources.

Browse Bathroom Remodeling

What You'll Need

Caulking GunAmazon.ca
$8-$15 CAD
$10-$15 CAD
$40-$80 CAD
$40-$80 CAD

Prices are estimates in CAD. Links may contain affiliate partnerships.

Difficulty Level

Moderate

Requires some research and planning. Consider hiring a pro for complex aspects.

Cost Guide

See what Ontario homeowners pay for bathroom remodeling services in 2026, with price breakdowns by service type.

View Bathroom Remodeling Costs